Post od vkrivoshiev »

Often when entering manual combinations, the program duplicates the combinations when recalculating the model when the option to load combinations is enabled.This is obtained when recalculating according to Eurocode.
K-Engineering Varna Ltd
Bulgaria, Varna
b.milan
Site Admin
Postovi: 2223
Pridružio se: Čet Jun 01, 2006 5:53 pm
Lokacija: Beograd
Kontakt:

Re: Tower build 8599

Post od b.milan »

When the option "Import load combinations from the depot after the analysis" is selected, the program adds combinations saved in the depot but skips combinations that already exist.
Comparison of the equality of combinations is performed according to the coefficients and ordinal numbers of the load cases.

Is it a seismic calculation using the multimodal method or the transverse force method?
Is it a simple model or a model with nonlinear behavior?
RADIMPEX SOFTWARE TEAM
vkrivoshiev
Postovi: 36
Pridružio se: Čet Nov 01, 2012 8:32 am
Lokacija: Bulgaria, Varna

Re: Tower build 8599

Post od vkrivoshiev »

I create the combinations manually and save them in the depot.
Check option to load from depot and the program adds the loaded combinations many times with each recalculation.
If i have 5 combination, after 5 recalculation, result is 25 combination.

Model is simple with seimic calculation. I use BDS-2012 and EC8 seismic calclulation with 1 and 3 spectrums.

Isn't the point of this option to delete the previous combinations and load them from the repository(with seismic comb) to automate the recalculation process?
K-Engineering Varna Ltd
Bulgaria, Varna
vkrivoshiev
Postovi: 36
Pridružio se: Čet Nov 01, 2012 8:32 am
Lokacija: Bulgaria, Varna

Re: Tower build 8599

Post od vkrivoshiev »

There is no such problem in the new build 8.599.9. Thank you.